1 Remove soil
2 Add a laver of hardcore and compact
3 Set formwork for 3m x 8.2m base
4 Pour outer frame using 30n concrete
5 Install a damp proof membrane
6 Pour floor using 30n concrete
7 Remove formwork once the concrete is set
8 Complete the infill once the shed has been installed